NewsPhotos: Progress continues on Anfield Road Stand expansion
The central and east cores are well under way, with formwork surrounding the central core being prepared to receive concrete.
Lift shaft number four is complete and reaches around 40 feet above the ground, to serve all floors and the roof level.
Work on the stand expansion, which will add around 7,000 seats to the stadium’s overall capacity, began last September and is nearing its first six-month milestone.
Developing behind the existing Anfield Road Stand allows full capacity on matchdays to continue without any disruption. Completion of the works is anticipated ahead of the 2023-24 season.
See the latest progress on-site in the images below.
Latest news
AcademyU18s match report: Comeback at Birmingham sends Liverpool to PL Cup quarter-finals
MatchThe opposition lowdown: Southampton
Interview'We can't take our foot off the gas' - Caoimhin Kelleher previews Southampton v Liverpool
Play nowCaoimhin Kelleher birthday quiz: Can you get 9/9?
FeatureClinical Harvey, Robbo's 'bullet' and Danns shock - things spotted in Friday's training